2016-01-26 - 23494 - Rel Notes - MTO lot sizing std functionality AFS6.5 #SAPReleases2016

Release Notes - Draft / Final


23494 : MTO lot sizing std functionality AFS6.5


Admin Info



Purpose
MTO lot sizing std functionality AFS6.5
Release No
001
Submitted on
01/26/2016
Submitted by
Laxman
Environment
NECNED to NEQ
Sent To
Babu
Object(s) created by
Laxman
Object(s) tested by
Laxman
Transport Status
Created in NECNED300 / 100

Transport and Technical Objects


Sl.
Transport ID
Description
Object Name
1
NEDK932749
PP:23494-Modify lot sizes to activate MRP MTO lot size
/AFS/PP_PPL









Release Notes


For Infrastructure


For Requestor




Test Notes


System : NECNED300

S. No
Material
Demand Type
T.Code/Program
Actual output
Expected output
P/F
SO
1
10023079
PIR
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

2
10023080
PIR
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

3
10023095
PIR

MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

4
10023081
PIR
RMMRP000
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

10023082
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

10023083
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

10023084
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

10023085
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

5
10023088
MTO
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P
73615
6
10023089
MTO
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P
73617
7
10023090
MTO
/AFS/MD02
Each Material should Create different lot Spilit
During MRP Run lot Size Sucessfully Splited
P
73619
10023091
Each Material should Create different lot Spilit
During MRP Run lot Size Sucessfully Splited
P
8
10023092
MTO
/AFS/MD02
Each Material should Create different lot Spilit
During MRP Run lot Size Sucessfully Splited
P
73620
10023093
/AFS/MD02
Each Material should Create different lot Spilit
During MRP Run lot Size Sucessfully Splited
P



System: NECNEQ100



S. No
Material
Demand Type
T.Code/Program
Actual output
Expected output
P/F
SO
1
10705840
PIR/MTS
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

2
10705841
PIR/MTS
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

3
10705842
PIR/MTS
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

4
10705843
PIR/MTS
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

5
10705844
PIR/MTS
RMMRP000
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited


6
10705845
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited


7
10705846
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited


8
11123866
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited


9
11123867
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited


10
11123868
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited


11
70198358
MTO
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P
2027933
12
70201696
MTO
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P
2027934
13
11123869
MTO
RMMRP000
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited

2027935
14
11123870

15
70201697

16
79532495
MTO
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P
2027936
17
11123871
MTO
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P
2027936
18
11123872
MTO
RMMRP000
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited

2027937
19
11123873
MTO
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited

2027938
20
11123874
MTO
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited

2027939
21
11123875
MTO
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited


Reference Document (Specification or Production Support Break Fix)



Specification

S.NUM
Material
Demand Type
T.Code/Program
Actual output
Expected output
P/F
SO
1
10023079
PIR
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

2
10023080
PIR
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

3
10023095
PIR

MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

4
10023081
PIR
RMMRP000
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

10023082
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

10023083
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

10023084
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

10023085
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P

5
10023088
MTO
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P
73615
6
10023089
MTO
/AFS/MD02
MRP run& Lot Size Should split
During MRP Run lot Size Sucessfully Splited
P
73617
7
10023090
MTO
/AFS/MD02
Each Material should Create different lot Spilit
During MRP Run lot Size Sucessfully Splited
P
73619
10023091
Each Material should Create different lot Spilit
During MRP Run lot Size Sucessfully Splited
P
8
10023092
MTO
/AFS/MD02
Each Material should Create different lot Spilit
During MRP Run lot Size Sucessfully Splited
P
73620
10023093
/AFS/MD02
Each Material should Create different lot Spilit
During MRP Run lot Size Sucessfully Splited
P